Case study | Construction Inspection
Raab Avenue Construction Inspection
Details
Owner
City of Belleville, Illinois
Client
City of Belleville, Illinois
Project Cost
$714,000
Status
Completed 2020
Summary
Kaskaskia Engineering Group, LLC (KEG) provided construction inspection for the improvements of Raab Avenue from 11th Street to 17th Street, in the City of Belleville, Illinois. The improvements provided ADA-compliant sidewalks along Raab Avenue, driveways for local residents, a resurfaced road, and new inlets at some intersections.
Project
KEG served as the Resident Engineer for the construction inspection for the construction of the accessible sidewalks, inlet removal and replacement, and new asphalt overlay. KEG was responsible for all coordination between the contractor and the City. All testing of materials and documentation of work was done in accordance with IDOT standards. KEG was also responsible for inspecting workmanship and dealing with the day-to-day issues that occurred onsite.